Busway Contract Descriptions
|
|
Contract 1
|
|
Contract 1 (Project No. 088-177) includes construction of a portion of
the Busway, beginning at Main Street (STA. 9+60) and running northerly
to an end point just south of Stanley Street in New Britain, CT (STA.
36+25). Contract 1 also includes the construction of the downtown New
Britain station, the demolition of the existing railroad bridge over
Route 9, a new busway bridge over Route 9, 5 retaining walls, and
reconstruction of the Route 72 eastbound Off-ramp and Route 9 southbound
on-ramp at Route 71 (Truman Overpass)
|
|
Contract 2
|
|
Contract 2 (Project Nos. 088-178 and 093-166) includes construction of a
portion of the Busway, beginning just south of Stanley Street in New
Britain, CT (STA. 36+25) and running northerly to an end point just
north of Cedar Street in Newington, CT (STA. 151+41). Contract 2 also
includes the construction of two stations, two new busway bridges, 16
retaining walls, and the replacement of the existing Cedar Street (Route
175) bridge over the busway.
|
|
Contract 3
|
Contract 3 (Project Nos. 93-180 and 63-643) includes construction of
a portion of the Busway, beginning just north of Cedar Street in
Newington, CT (STA. 151+41) and running northerly to an end point
just north of Sigourney Street in Hartford, CT (STA. 459+00).
Contract 3 also includes the construction of 7 stations, 8 new
busway bridges, 44 retaining walls, 2 culverts to be jacked under
existing operating Amtrak tracks, a new bridge at Flatbush Avenue in
West Hartford via grade separation, and the construction of a new
gravel access road for Amtrak (AAR).
|
|
Contract 4
|
|
Contract 4 (Project No. 063-670) includes construction of a portion of
the Busway, beginning just north of Sigourney Street (STA. 459+00) and
running northerly to an end point at Asylum Street in Hartford, CT (STA.
490+59). Contract 4 also includes the construction of 1 station, 2 new
busway bridges, 10 retaining walls, and the relocation of approximately
one mile of railroad (Capitol Avenue to Union Station).
|
|
Contract 5
|
|
Contract 5 (Project Nos. 063-671 and 063-641) includes replacement of
the existing Broad Street bridge over Amtrak, 3 retaining walls, and the
reconstruction of Broad Street between Capitol Avenue and Farmington
Avenue in Hartford, CT.
|
|
|
|
Busway
by Contract, South Section
(Click thumbnail to open full map) |
|
|
|
| |
Busway
by Contract, North Section
(Click thumbnail to open full map) |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
PLEASE
NOTE: To submit
a bid, prospective bidders for this project
must be prequalified
with the State of Connecticut. Bidding,
award, and prequalification information can be found via links at right. |
 |
|
|
|
|
 |
|
|
|
|
 |
|
|
|
Busway Home
|
CTDOT Home
|
CT.gov Home |
Stay Informed |
Contact Us
State of Connecticut
Disclaimer, Privacy
Policy
Copyright © 2012 Michael Baker Engineering, Inc.
|
 |