NOVEMBER 3, 2011

Project No. 063-669 (Utility Relocation Flatbush Avenue over Busway and Amtrak) Ludlow Construction Company, Inc. 

 

WATER MAIN RELOCATION - NIGHTIME CONSTRUCTION (HARTFORD / WEST HARTFORD)

Detour of Flatbush Avenue between New Park Avenue and Ahern Street.  Thursday 11/3 through Friday 11/11, between the hours of 8 PM and 6 AM

For specific relocation questions, contact Mr. David Kingsbury, Chief Inspector: David.Kingsbury@ct.gov  

 

OCTOBER 12, 2011

Project No. 063-669 (Utility Relocation Flatbush Avenue over Busway and Amtrak) Ludlow Construction Company, Inc. 

 

Work Begins for The Relocation of Utilities along Flatbush Avenue, New Park Avenue and Newfield Avenue in the cities of West Hartford and Hartford

The Connecticut Department of Transportation is announcing that beginning on Wednesday, October 12, 2011 motorists can expect nighttime and weekend lane restrictions along Flatbush Avenue, New Park Avenue and Newfield Avenue in West Hartford and Hartford as part of the utility breakout project to relocate water and sewer mains.  

Lane Closure Info- Motorists can expect lane closures Monday through Friday during nighttime hours from 8 p.m. to 6 a.m. with daytime closures (currently not scheduled) between the hours of 9 a.m. and 3 p.m.   Weekend work may also occur at any time.

  • Flatbush Avenue between Ahern Street and west of Newfield Street before SR504 (Will J. Hilliard Memorial Highway) which is the connector to I-84.

  • New Park Avenue at Flatbush Avenue intersection

  • Newfield Avenue from Flatbush Avenue to vicinity of Mahoney Drive

 

OCTOBER 7, 2011

Project No. 063-669 (Utility Relocation Flatbush Avenue over Busway and Amtrak) Ludlow Construction Company, Inc. 

 

WATER MAIN RELOCATION - NIGHTIME CONSTRUCTION

─ West Hartford: across intersection of Flatbush Avenue & New Park Avenue (MAP HERE)

─ Night time construction on Wednesday October 12, 2011 between the hours of  8:00 p.m. to 6:00 a.m.

─ Work will run from Wednesday Oct. 12 to Friday Oct. 14, beginning again Sunday Oct.16 to Fri. October 21

─ One lane traffic will be maintained through the intersection

─ Expect periods of delays as material is moved

─ Traffic control will be maintained by West Hartford police department

 

For specific relocation questions, contact Mr. David Kingsbury, Chief Inspector: David.Kingsbury@ct.gov  